DSM (Third Amendment) Regulations, 2026: general-seller treatment for new RE

  • CERC
  • 25 August 2026
  • No. L-1/260/2021/CERC
StorageEMSSolarGrid

What it says

Ends the softer deviation treatment for new wind and solar, and sets a rate for standalone storage's trial-run power. In force from 31 August 2026.

Key provisions

  1. Wind and solar sellers are charged as general sellers if the tender or bid date is on or after 1 January 2027.
  2. Other wind and solar projects move to general-seller treatment if commissioned on or after 1 January 2029.
  3. Power a standalone storage system injects between first synchronisation and end of trial run is paid at the normal deviation rate, capped at ₹2.00/kWh.
  4. Deviation for standalone pumped storage under Section 62 is priced at its energy charge rate.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy