It has to follow the buying entity's schedule and the dispatch centre's signals at the delivery point, and hold back enough energy to answer every scheduled block. It also has to compute availability, round-trip efficiency and cycles from the delivery-point meter, using the contract's own formulae. Ingro EMS-GS does this on a redundant controller pair at the substation, and keeps battery-health records for lenders and insurers.
The developer has bid a capacity charge under a contract that pays for capacity made available, block by block. It deducts damages linked to that charge for any shortfall and penalises round-trip efficiency below the guarantee. Alongside it sit a cell warranty with its own cycle and state-of-charge limits, grid rules adding secondary control, grid-forming and black start for larger plants, cyber-security regulations, and a commissioning date backed by liquidated damages.
Written for
Developers bidding grid-scale BESS tenders, their EPC contractors and integrators, and the owners' and lenders' engineers reviewing them
What it costs you today
Availability is actual energy over scheduled energy in each block the buyer scheduled. If state of charge is short when a block arrives, it counts against the plant even with every container healthy.
The contract may let the buyer split sessions, run at reduced power or call extra cycles, and new construction standards say cooling-off periods must not limit flexible operation. The cell warranty may still cap throughput, SoC window or rest time, and the developer carries the gap.
Round-trip efficiency is settled monthly at the meter, with the auxiliary load counted inside it. In an Indian summer the cooling load can turn a datasheet efficiency into a monthly penalty.
Substation automation approval, SCADA integration and telemetry must all be in service before the trial run counts. Developers have been refused extensions and handed liquidated damages when these slipped.
A tendered storage plant is paid against contracted availability. EMS-GS follows the operator's schedule, responds as the connection agreement requires, and records every instruction and response as evidence.
Scheduled dispatch
Illustrative. Not measured data.
The dashed line is the operator's schedule: charge, discharge, charge, discharge. The plant follows it block by block, and each block is recorded with any deviation.
On top of the schedule, the plant adjusts its output for frequency and reactive power response as the connection agreement requires. The schedule, the response and the record stay separate and traceable.
Dispatch instructions executed and deviations recorded to the operator's format and timing.
Frequency and reactive power response as required by the connection agreement.
Availability and cycle counts recorded and evidenced monthly against the contracted values.
Battery state-of-health and warranty records maintained for lenders and insurers.
Leave your details. An Ingro engineer gets back to you within one business day, no obligation.
The controller is half of it. The other half is the engineering that puts it on your site and keeps it right afterwards. Both are quoted as one item.
The product
1. The controller
Wired, configured and commissioned against your plant, and installed in the plant room. It is the component that operates the site.
2. The operator console
A single-line representation of the actual plant with live power on every feeder, the state of each source, the alarm register, and the endurance available at the load currently being carried.
3. The mobile view
Read-only, for management rather than operations: whether the site is sound, what it has saved, what has occurred and what is scheduled.
4. Reporting and training
The reporting suite, generated and distributed automatically, and instruction for the personnel who will operate the plant.
The service
The platform in full: specifications, the thirteen reports and implementation
9 questions
It has to prove itself. A tendered storage plant is paid against contracted availability, so the controller must execute dispatch instructions and record deviations in the operator's own format and timing, deliver frequency and reactive power response to the connection agreement, and evidence availability and cycle counts monthly against the contracted values.
Requirements differ by state and by round, so we scope against the tender document rather than against the category. Send the document and we will write the scope of supply against what it actually asks for.
Yes. Ingro EMS is supplied to BESS integrators, EPC contractors and developers to go inside the storage they build. Ingro also supplied the EMS and SCADA technology on India's first grid-scale BESS, the 10 MW / 10 MWh plant at Tata Power-DDL's Rohini substation in Delhi.
Many standalone capacity contracts forbid using the contracted capacity for anything else, so on those there is little to give up. Where the contract allows other use outside the buyer's windows, the reserve floor and the cycle cost decide how much is traded. Both are settings the owner keeps.
With a record kept from day one: state of health per block, throughput against the warranty envelope, and the SoC window enforced on every cycle. Ingro EMS-GS reports these against the guarantee each month, so the cell supplier, lender and insurer all read the same figures.
From the historian and the energy ledger, not from a spreadsheet. Availability and cycle counts are recorded continuously and issued monthly, and state-of-health and warranty records are maintained alongside them, each figure carrying its basis — metered, derived or modelled — and the proportion of the period covered by data.
Tenders differ by state and by round, but they describe the same kinds of obligation: executing dispatch schedules, delivering frequency and reactive power response under the connection agreement, and evidencing availability, cycle counts and battery health against contracted values. We scope against the tender document itself.
The developer holds the availability and round-trip risk, so the EMS has to compute the contract's formulae, not just protect the DC block. A bundled EMS can work if it does that, meets any indigenous application-software clause, and is licensed to the project. Ingro EMS can also be supplied inside the integrator's scope.
The statutory regulations apply by plant size, so check the threshold against your capacity. Tender annexures can still call for the CEA cyber-security guidelines regardless of size, and grid procedures for ancillary services ask for a cyber-security undertaking. Ingro scopes against the tender document, clause by clause.