ALMM List-II for solar PV cells

  • MNRE
  • 9 December 2024
  • O.M. No. 283/59/2024-GRID SOLAR
Solar

What it says

A second Approved List of Models and Manufacturers, for cells. From 1 June 2026, modules on List-I used in eligible projects must use List-II cells.

Key provisions

  1. ALMM List-II for solar PV cells takes effect from 1 June 2026.
  2. Projects that must use ALMM List-I modules must use modules made with List-II cells from that date.
  3. Projects whose bids closed on or before the order are exempt from the cell condition, whatever their commissioning date.
  4. Net-metering and open-access projects commissioned before 1 June 2026 are exempt (later extended to 31 December 2026).
  5. Thin-film modules from integrated List-I manufacturers are treated as compliant.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy