A second Approved List of Models and Manufacturers, for cells. From 1 June 2026, modules on List-I used in eligible projects must use List-II cells.
Key provisions
- ALMM List-II for solar PV cells takes effect from 1 June 2026.
- Projects that must use ALMM List-I modules must use modules made with List-II cells from that date.
- Projects whose bids closed on or before the order are exempt from the cell condition, whatever their commissioning date.
- Net-metering and open-access projects commissioned before 1 June 2026 are exempt (later extended to 31 December 2026).
- Thin-film modules from integrated List-I manufacturers are treated as compliant.