What it says

Sets up the Approved List of Models and Manufacturers. Covered projects may only use enlisted modules. Held in abeyance for FY 2023-24 and applied again from 1 April 2024.

Key provisions

  1. List-I covers solar PV modules; makers need BIS registration before enlistment.
  2. Applies to government and government-assisted projects, scheme projects and projects selling power to government.
  3. Extended to net-metering and open-access projects from 1 October 2022; behind-the-meter captive plants excluded.
  4. Held in abeyance for FY 2023-24 and applied again from 1 April 2024.
  5. Since May 2023, minimum module efficiency of 20% for utility scale, 19.5% for rooftop and pumping, 19% for lighting.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy