What it says
Sets up the Approved List of Models and Manufacturers. Covered projects may only use enlisted modules. Held in abeyance for FY 2023-24 and applied again from 1 April 2024.
Key provisions
- List-I covers solar PV modules; makers need BIS registration before enlistment.
- Applies to government and government-assisted projects, scheme projects and projects selling power to government.
- Extended to net-metering and open-access projects from 1 October 2022; behind-the-meter captive plants excluded.
- Held in abeyance for FY 2023-24 and applied again from 1 April 2024.
- Since May 2023, minimum module efficiency of 20% for utility scale, 19.5% for rooftop and pumping, 19% for lighting.