What it says

Charges for deviating from schedule in the inter-state grid, with separate rules for wind and solar, standalone storage and co-located storage. In force from 16 September 2024.

Key provisions

  1. Solar and hybrid sellers' first deviation band was 10% of schedule until 31 March 2026, and 5% from 1 April 2026.
  2. Wind sellers' first band narrows from 15% to 10% on the same date.
  3. Standalone storage is charged as a general seller; in charging mode, over-drawal is treated as under-injection and the reverse.
  4. Solar or wind with storage at one connection point is settled as an RE seller while the plant injects, and as standalone storage when only the battery runs.
  5. Each generator and storage unit needs its own special energy meter; sellers at a pooling station may use a Qualified Coordinating Agency.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy