Indian Electricity Grid Code, 2023

  • CERC
  • 29 May 2023
  • No. L-1/265/2022/CERC
StorageEMSSolarGrid

What it says

A new grid code for planning, connection, commissioning, scheduling and operation, treating energy storage as its own class of grid user. In force from 1 October 2023.

Key provisions

  1. A standalone storage trial run is one full charge-discharge cycle with metering, telemetry and protection in service.
  2. Storage must certify CEA connectivity compliance and pass tests for MW/MWh capability, frequency response and ramping.
  3. A solar trial run needs at least four hours of power flow with the plant controller, telemetry and protection in service.
  4. All RE plants and storage must control active-power injection as CEA standards require.
  5. RE and storage at ISTS substations may appoint a QCA for scheduling; RLDCs forecast wind, solar and storage output.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy