ISTS charges waiver phased out for RE; co-located BESS exempt to June 2028

  • CERC
  • 26 June 2025
  • No. L-1/250/2019/CERC
StorageSolarGrid

What it says

The CERC (Sharing of Inter-State Transmission Charges and Losses) (Fourth Amendment) Regulations, 2025 step down the waiver for new solar and wind after 30 June 2025. Storage charged from a co-located RE plant keeps a full waiver to June 2028.

Key provisions

  1. Solar, wind and hybrid plants operating by 30 June 2025 get a 100% waiver for 25 years; then 75%, 50% and 25% for each later year to June 2028, and nothing after.
  2. BESS at an RE substation and charged from that plant gets a 100% waiver for 12 years if commissioned by 30 June 2028.
  3. Other BESS steps down from 100% to 0% on the same yearly dates.
  4. Co-located batteries may draw up to 10% of yearly charging energy from the grid in contingencies.
  5. Pumped storage gets a 25-year waiver if construction is awarded by 30 June 2028.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy