Electricity (Rights of Consumers) Amendment Rules, 2024: faster rooftop solar

  • Ministry of Power
  • 22 February 2024
  • G.S.R. 125(E)
SolarGrid

What it says

Rooftop solar up to 10 kW no longer needs a technical feasibility study, and larger systems get shorter discom deadlines.

Key provisions

  1. Complete rooftop applications up to 10 kW are deemed accepted without a feasibility study.
  2. For systems up to 10 kW, the discom must raise the sanctioned load where needed.
  3. For larger systems the feasibility study must finish within 15 days, or the proposal is deemed feasible.
  4. After the installation certificate, the discom has 15 days to sign the agreement, fit the meter and commission.
  5. The discom must offer a separate connection for EV charging on request.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy