Implementing agencies and state utilities are advised to require co-located storage in future solar tenders: at least 2 hours, sized at 10% of solar capacity.

Key provisions

  1. Minimum 2-hour co-located storage equal to 10% of installed solar capacity in future tenders.
  2. Storage may cycle once (charged from solar for the evening) or twice (also charged from the grid in low-demand hours).
  3. Bid documents should include a way to check that storage is available outside solar hours.
  4. Distribution licensees may consider 2-hour storage for rooftop solar.
  5. A later CEA clarification said it applies only to future tenders.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy