What it says
₹5,400 crore from the Power System Development Fund for 30 GWh of BESS: 25 GWh across 15 states and 5 GWh for NTPC. An August 2025 amendment requires EMS software developed in India and bars refurbished cells.
Key provisions
- VGF of ₹18 lakh per MWh for 30 GWh of BESS, ₹5,400 crore in all, funded entirely from the Power System Development Fund.
- 25 GWh across 15 states (Rajasthan, Gujarat and Maharashtra 4,000 MWh each; Karnataka and Andhra Pradesh 2,000 MWh each; others 500–1,500 MWh) and 5 GWh for NTPC.
- Projects are bid on tariff under Section 63, BOO/BOOT, preferably for 12–15 years; the reference design is 2 hours at about 1.5 cycles a day.
- Commissioning within 18 months of the BESPA; VGF paid 20% at financial closure, 50% at COD and 30% after one year of operation.
- Amendment of 4 August 2025: the EMS application software must be developed in India, and refurbished cells are not allowed.
- Amendment of 22 September 2025: financial closure within 6 months of the BESPA; an insurance surety bond may replace the bank guarantee.