Skipper Limited, a leading Indian manufacturer of transmission & distribution structures, PVC pipes, and engineering plastics, engaged Ingro Energy to design the Energy Management System and SCADA for a hybrid Solar + BESS plant. The plant pairs a 35 MW solar PV facility with a 5 MW / 10 MWh Battery Energy Storage System, and the design places the EMS as a slave to the Plant Power Controller (PPC), which communicates with the State Load Dispatch Centre.
This project showcases Ingro's capability to engineer cost-optimized, standards-compliant EMS designs for hybrid renewable energy plants, with detailed BOM engineering, multi-vendor evaluation, and comprehensive architecture design.
Multi-system coordinationSolar inverters, BESS PCS, BMS, HVAC, fire suppression, and grid protection from different OEMs must be unified
PPC hierarchy complianceEMS as slave under the Plant Power Controller with precise IEC 61850, Modbus TCP, IEC-104 protocol implementation
2-Block architecture, each block requiring a field RCP connected to central MCP via fiber ring topology
BESS-specific I/OBMS cell-level data via CAN-to-Modbus gateways, PCS parameters, HVAC, fire/gas detection sensors, and safety interlocks
Cost optimization pressureLowest possible EMS cost without compromising reliability or compliance
What Ingro put in place, step by step.
Complete OT network, MCP with redundant L3 switches, 2× RCPs, fiber ring backbone, FortiGate firewall, GPS time server, IEC-104 gateway
10-sheet workbook with 239 formulas, zero errors, and 3-tier vendor alternatives for every component
CAN-to-Modbus gateways for BMS, Pilz safety relays, additional I/O for HVAC and fire suppression
Mapped ~2,126 total tags across all devices, hardwired and protocol-based
Final BOM at ₹52.16 Lakhs (₹1.49L/MW), 12% lower than competing quote while covering 10 critical gaps
More of our energy storage and optimisation work.