Ingro EMS-EV · Energy management system

EMS for EV Charging Hubs

Fit more chargers on the connection you already hold: canopy solar first, the battery for the plug-in rush.

Works with: Chargers + battery + solar + supply

ingroingro1234Ingro EMS5
The question buyers ask

How can I add more EV fast chargers when my sanctioned load or transformer doesn't have the capacity?

Put a battery behind the chargers and a controller over both. Vehicles draw from canopy solar first; when several plug in together, the battery supplies the peak above the sanctioned load, so the connection never sees it and each bay still delivers full power. The battery refills in quieter or cheaper hours. Ingro EMS-EV also records energy per charger for billing.

They have a charger plan and a connection that cannot carry it: a sanctioned load too small, a transformer the DISCOM says needs augmenting, or a host building already close to its contract demand. The upgrade means a bigger deposit, civil work and months of waiting while vehicles or customers are already arriving. They want to open on the connection they have, without slowing sessions until customers drive off or buses miss departures.

Written for

Charge point operators, fleet and bus-depot operators, fuel retailers and host sites (malls, offices, hotels) adding chargers on a limited connection

What it costs you today

  • Upgrade quote, deposit and the wait

    An enhancement can mean a new transformer, cable or HT connection, a security deposit that rises with sanctioned load, and a lead time that often outruns vehicle delivery. Depot timelines slip on the connection, not the buses.

  • Everyone plugs in at once

    A fleet returns together and a forecourt fills in the evening. The connection has to carry that rush, though chargers in India are used only a few percent of the day. Where the host building is billed on maximum demand, one busy interval also sets its charge for the month.

  • Throttling costs sessions and departures

    Software load balancing keeps the site under its limit by slowing every session at the busy hour. On short dwell that means fewer vehicles served; at a depot it risks a bus not ready for its slot.

  • No idea which bay pays

    At host sites the electricity bill sits with the landlord, and charger meters are rarely reconciled against it. The operator cannot see energy cost, losses or utilisation bay by bay.

How it works

How do more chargers fit on the same connection?

A charging hub's demand is spiky: several vehicles plug in at once. EMS-EV runs the chargers from canopy solar first and lets the battery take the coincident peaks, so the connection never sees them.

With the battery

Illustrative. Not measured data.

Connection limit
Battery state of charge
NightMorningMiddayEveningNight
  • Charging demand
  • Connection limit
  • From the connection
  • Canopy solar
  • Battery discharging
  • Battery charging

Solar covers what it can. When a rush of plug-ins pushes demand toward the connection limit, the battery supplies the difference, then recharges from solar and spare headroom before the next rush.

Order of preference in a plug-in rush

  1. 1Canopy solarReduces what the connection has to deliver.
  2. 2The supply, up to its limitNever asked for more than the connection allows.
  3. 3The battery, above the limitMore charger capacity on the connection you already hold.
What it does for the business

The Outcomes EMS-EV Delivers

  1. Solar first

    Vehicles charged from canopy solar first, reducing energy drawn from the connection.

  2. Plug-in peaks absorbed

    Coincident plug-in peaks supplied by the battery, keeping demand within the connection limit.

  3. More chargers, same connection

    Higher charger capacity on the existing connection, without a sanctioned-load enhancement.

  4. Energy accounted per charger

    Energy accounting per charger for billing and utilisation analysis.

What an Indian charging hub has to get right

The Details That Decide a Charging Hub

Most advice on charging hubs is written for markets where the demand charge is the enemy. In India the rules, the tariffs and the failure modes are different. These are the points that decide whether a hub opens on time and earns.

  • The tariff rewards daytime, not low peaks

    The Ministry of Power's 2024 guidelines cap the public-charging tariff at a single-part rate no higher than the Average Cost of Supply, with solar hours (9 am to 4 pm) at 0.7 times that cost and other hours at 1.3 times. A kilowatt-hour bought at noon costs about 54% of one bought in the evening. For a hub the case is rarely demand-charge shaving. It is fitting more chargers on the connection, buying in the cheap window and staying open.

    Mercom, 20 Sep 2024
  • Chargers sit idle, so the connection is the costly part

    Public chargers in India are used for only a few percent of the day: reported utilisation is 1 to 5%, and below 2% in a FICCI estimate. A connection sized for charger nameplate pays for capacity that is idle nearly all day. A smaller connection with a battery sized for the real coincident rush is the capital-efficient shape.

    IANS, Sep 2026
  • Chargers do not always obey the limit

    Field testing of more than 45 charger brands found common faults: the station-wide power limit is often not implemented, some chargers reply "accepted" and ignore it, some confuse watts and amps, and some return to full power after a network drop. A limit set only in software cannot be trusted on a mixed-brand site. Holding it from the connection-point meter, with the battery covering what a charger ignores, can.

    Ampcontrol, Aug 2026
  • The charging platform and the EMS must not fight

    The charging management system handles authorisation, sessions and pricing. OCPP 1.6 has no native way for a local controller to feed a limit into it. OCPP 2.0.1 adds an external-constraints profile and a notification so the platform can see the limit a local controller set. Ask any supplier which version it works with and where it sits relative to your platform.

    Solidstudio, OCPP migration
  • Outages keep chargers offline too

    One Indian charge point operator reports that more than 10 to 12% of its chargers cannot charge at any moment because of power outages, worse outside the metros and on highways. A hub that sells reliability is selling hours open, not only kilowatts.

    EVreporter, 14 Apr 2025
  • The connection wait is set in rules, and the long ones bite

    The 2024 guidelines set connection timelines of 3 days in metros, 7 in other municipal areas, 15 in rural and 30 in hilly areas, up to 90 days where a mains extension or new substation is needed. Multi-megawatt depots needing new high-tension works can take far longer, and depots above 1 MW need load-flow and fault studies with the utility.

    Down To Earth, 3 Jul 2024
  • Bus depots: schedule first, battery second

    A depot of about 100 buses needs 4 to 5 MW of charging, mostly between midnight and 5 am, on one estimate. Charging each bus to its departure time brings the real peak far below charger nameplate, and the battery covers what is left, such as early departures that squeeze the window. Under PM-eBus Sewa the central government pays for the behind-the-meter power works inside the depot, but not the chargers.

    ORF, 11 May 2026
  • At a forecourt, battery power sets the size, not energy

    Short-dwell sites ask for a lot of power for a short time. A published sizing method tests the first hour: with 30 kW of grid per port and 150 kWh to deliver per port, you need at least 120 kWh of storage per port. The converter rating, and how fast the cells can discharge, usually decide the battery before the kilowatt-hours do.

    NREL, 2024
  • Fire rules for parking differ by city

    Mumbai's 2024 fire guidelines bar charging in automated parking and basements, with some reports allowing the first basement. Haryana allows basements with Fire Department and utility certification, and Bengaluru allows them with a fire NOC. At malls and offices the battery usually has to sit at grade or outdoors, which shapes the layout before the electrical design starts.

    Autocar India, Haryana rules

Worked example

A highway forecourt: 4 chargers on a 100 kW connection

Illustrative. The connection, charger and traffic figures are assumptions chosen for the example, not a measured site.

  1. 1. Assumptions

    100 kW connection · 4 chargers of 60 kW · 5 kW of auxiliaries · 94% charger efficiency · 12 evening sessions of 25 kWh

    Nameplate 240 kW

  2. 2. Peak with 3 cars at full power

    3 × 60 ÷ 0.94 + 5

    197 kW

  3. 3. Gap above the connection

    197 − 100

    97 kW, so a battery converter of about 100 kW

  4. 4. Cars at full power, connection alone

    100 ÷ (60 ÷ 0.94)

    about 1.5 cars, against 3 with the battery

  5. 5. Evening energy from the battery

    12 × 25 ÷ 0.94 + 15 = 334 kWh, less 100 kW × 3 h = 300 kWh from the grid

    34 kWh. But a 100 kW converter on 34 kWh is about 3C, so power sets the size: roughly 100 to 200 kWh of cells

  6. 6. Value of shifting energy between tariff windows

    ACoS assumed at ₹7/kWh: solar hours ₹4.90, evening ₹9.10. 34 × (9.10 − 4.90 ÷ 0.88)

    about ₹44,000 a year

What it shows: Shifting energy between tariff windows is worth little here, about ₹44,000 a year. The battery earns its place by doubling the cars that can charge at full power on the connection you hold, and by avoiding a high-tension upgrade and its wait. Size it on power, then check the energy.

Want an engineer to call you?

Leave your details. An Ingro engineer gets back to you within one business day, no obligation.

Or tell us about your site ↓
Product + service

What Comes With Ingro EMS-EV?

The controller is half of it. The other half is the engineering that puts it on your site and keeps it right afterwards. Both are quoted as one item.

The product

ingroENERGY MANAGEMENTEMS-EV · liveIngro EMS-EVController · console · reporting
  1. 1. The controller

    Wired, configured and commissioned against your plant, and installed in the plant room. It is the component that operates the site.

  2. 2. The operator console

    A single-line representation of the actual plant with live power on every feeder, the state of each source, the alarm register, and the endurance available at the load currently being carried.

  3. 3. The mobile view

    Read-only, for management rather than operations: whether the site is sound, what it has saved, what has occurred and what is scheduled.

  4. 4. Reporting and training

    The reporting suite, generated and distributed automatically, and instruction for the personnel who will operate the plant.

The service

  1. 1The site is establishedWhat exists, what has been ordered, and the outcomes the plant is required to deliver. One schedule and one conversation.
  2. 2The equipment schedule is issuedWritten against those outcomes, so that the plant is capable of what has been asked of it.
  3. 3The plant is modelledYour asset counts, loads, tariff and load profile are run against a full simulation of the site before equipment ships, including adverse conditions. Behaviour is reviewed and revised at this stage.
  4. 4The plant is commissionedWired, configured and tested against the site's own values, with the results recorded.
  5. 5The plant is handed over and supportedPersonnel trained, the reporting suite in service, and a defined route for support thereafter.
Need the battery too? Ingro also delivers the whole system: sizing and simulation, equipment, EMS, installation, commissioning and O&M, as turnkey BESS. Already have a battery with a locked controller? Smart retrofit.

The platform in full: specifications, the thirteen reports and implementation

Common questions

EMS-EV, Answered

16 questions

By putting a battery behind the chargers and a controller in front of both. EMS-EV supplies coincident plug-in peaks from storage rather than the grid, so the connection never sees them — which allows more charger capacity on the existing sanctioned load instead of an enhancement application and the wait that comes with it.

It accounts per charger. Each charger's energy is metered and recorded for billing and utilisation analysis, so revenue and throughput can be attributed to individual units rather than to the site as a whole.

Bus depots, fleet yards, highway forecourts, forklift bays and mall parking.

The Ministry of Power's 2024 guidelines set 3 days in metro areas, 7 in other municipal areas, 15 in rural areas and 30 in hilly areas, and up to 90 days where a mains extension or new substation is needed. Multi-megawatt depots that need new high-tension works can take far longer.

For the behind-the-meter works, yes: the scheme gives 100% central assistance for the high-tension line and in-depot substation. It does not cover the chargers or the cabling from the meter to them. Check the current guidelines for eligibility dates.

Field testing of about 100 charger models found that site-wide power profiles are often not implemented, some chargers accept a limit and then ignore it, and some return to full power after a network drop. The answer is to test each model at commissioning and to hold the connection limit from the meter, not from charger promises.

Load balancing shares the connection by slowing sessions, which works where vehicles stand for hours, such as a depot overnight. Where dwell is short, slower sessions mean fewer vehicles served at the busy hour. A battery supplies the power above the limit so bays run at full rate, with charger modulation kept as the last resort.

Every cycle has a cost in battery life. The controller should weigh that cycle cost against what the cycle saves before taking it, keep cycling inside the warranty's throughput and state-of-charge limits, and report battery health against the guarantee so the time to add capacity arrives as a number.

Yes. A forecourt with canopy solar, storage and no connection at all is the same package configured differently — the order of preference closes up where the utility supply would have sat, and the site runs on generation and storage.

Vehicles charge from canopy solar first, which reduces the energy drawn from the connection. The battery then handles coincident plug-in peaks so demand stays inside the connection limit.

Yes, with a battery behind it. The connection refills the battery continuously and the battery supplies the difference while a vehicle charges. Whether it works depends on the busiest hour: the battery's power rating must cover the gap and its energy must last the rush. NREL's first-hour method puts a four-port site on 100 kW at about 500 kWh to deliver 600 kWh in its first hour.

One estimate puts a depot of about 100 buses at 4 to 5 MW of charging, mostly between midnight and 5 am. Scheduling each bus to its departure time brings the real peak well below charger nameplate, which is why scheduling comes before storage in depot design.

The charging management system, the OCPP back-end, handles authorisation, sessions, pricing and remote charger control. The EMS measures the site's connection point and controls the battery, solar and charger limits together. OCPP 2.0.1 lets a local controller set an external limit and tells the platform about it. OCPP 1.6 has no native way to do that.

It depends on the city. Mumbai's 2024 fire guidelines bar charging in automated parking and basements, with some reports allowing the first basement. Haryana allows basements with Fire Department and utility certification, and Bengaluru with a fire NOC. Check the local rule before planning where the battery and chargers go.

Often there is none, and the case should not rest on one. The Ministry of Power's 2024 guidelines cap public-charging tariffs at a single-part rate, with solar hours (9 am to 4 pm) at 0.7 times the average cost of supply and other hours at 1.3 times. Check your state's order, because rates differ. On that structure the case rests on opening bays on the connection you hold, avoiding the upgrade and its wait, and buying in the cheaper solar window. Behind a commercial connection that bills maximum demand, holding the peak adds to that case. A worked example further up this page shows that tariff shifting alone is worth little at a forecourt.

It can, provided the connection point is metered. The controller holds the combined import of building and chargers under the limit, so the host's contract demand is respected, and charger energy is recorded separately so it can be billed back to the operator or tenant.

Still have a question?

Share details of your site, hardware and tariff or tender, and an engineer will answer it.

Scope EMS-EV for Your Site

Send us what you have. We return a scope of supply, an equipment schedule and an indicative programme for EMS-EV, written against the outcomes you set.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy

Want numbers first? Simulate the site. See it on a project: Jio-BP charging hub.