Guidelines for procurement and use of battery energy storage systems

  • Ministry of Power
  • 10 March 2022
  • Resolution No. 23/16/2020-R&R Part (1)
StorageGrid

What it says

Standard bidding framework for BESS as generation, transmission or distribution assets and for ancillary services.

Key provisions

  1. Competitive bidding for BESS under Section 63 of the Electricity Act, on a Build-Own-Operate or Build-Own-Operate-Transfer basis.
  2. Minimum project size of 1 MW within a state and 50 MW for inter-state projects.
  3. Covers storage with transmission, for ancillary services, for distribution, standalone arbitrage and sale of storage capacity.
  4. Bids on an availability-based fixed charge or annuity, or on the VGF needed for a set tariff; single-stage, two-part, with e-reverse auction.
  5. Minimum BESPA term of 8 years, with payment security, performance parameters and penalties for shortfall.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy