StorageGrid
What it says
₹3,760 crore of VGF for 4,000 MWh of battery storage, to be built by 2030-31.
Key provisions
- 4,000 MWh of BESS with an outlay of ₹9,400 crore, of which ₹3,760 crore is central budgetary support.
- VGF of up to 40% of capital cost as a one-time grant.
- Projects must be commissioned within 24 months of the agreement; payouts run to 2030-31.
- Paid in five parts: 10% at financial closure, 45% at COD, then 15% in each of the first three years.
- Projects are awarded under the March 2022 BESS bidding guidelines, with at least 85% of capacity for discoms.