Viability gap funding for battery storage (first tranche)

  • Union Cabinet / Ministry of Power
  • Approved 6 September 2023; guidelines issued 15 March 2024
  • F.No. 42-26/1/2022-RCM (Part 1)
StorageGrid

What it says

₹3,760 crore of VGF for 4,000 MWh of battery storage, to be built by 2030-31.

Key provisions

  1. 4,000 MWh of BESS with an outlay of ₹9,400 crore, of which ₹3,760 crore is central budgetary support.
  2. VGF of up to 40% of capital cost as a one-time grant.
  3. Projects must be commissioned within 24 months of the agreement; payouts run to 2030-31.
  4. Paid in five parts: 10% at financial closure, 45% at COD, then 15% in each of the first three years.
  5. Projects are awarded under the March 2022 BESS bidding guidelines, with at least 85% of capacity for discoms.

Related notifications

All notifications

What does this mean for your site?

Tell us about your site and an engineer will reply with what this rule changes for you and how to make the most of it.

What are you looking for?

An engineer replies within one business day. Bills, drawings or data files can go in reply to that email, or to contact@ingroenergy.com. Privacy policy