    CEA

    Construction standards for BESS and RE plants, with EMS requirements (2026)

    The CEA (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2026 add standards for solar, wind and BESS, including the first statutory specification for a BESS energy management system. In force from 1 April 2027.

    What it changes: From April 2027 every BESS needs an EMS with SCADA integration, remote set-points and 90-day high-resolution logging; 50 MW and above also needs AGC, grid-forming and black start.

    StorageEMSBatteriesGridSolarOfficial PDFDetails
  2. Mar 2026

    CEA

    Safety regulations for battery energy storage systems (2026)

    The CEA (Measures relating to Safety and Electric Supply) Amendment Regulations, 2026 add a chapter on BESS safety. Published in the Gazette on 30 March 2026, in force from 1 April 2027.

    What it changes: Any BESS connected above 650 V must meet two-fault tolerance, cell-level monitoring, fire suppression and a third-party fire safety audit.

    StorageBatteriesEMSOfficial PDFDetails
  3. Dec 2025

    Ministry of Power

    Minimum 20% local content for BESS under the VGF scheme

    BESS tenders under the PSDF-funded VGF scheme must have at least 20% local content by project cost. The EMS software developed in India counts towards it.

    What it changes: Bidders for VGF-backed BESS must show at least 20% domestic value, and an Indian EMS helps meet it.

    StorageEMSBatteriesOfficial PDFDetails
  4. Jan 2025

    MNRE

    Solar Systems, Devices and Components Goods Order, 2025

    Replaces the 2017 compulsory registration order. Solar modules, solar storage batteries and PV inverters must meet Indian Standards and carry the BIS mark.

    What it changes: Modules, inverters and solar storage batteries sold in India need a BIS licence, so check certification before buying.

    SolarBatteriesStorageOfficial PDFDetails
  5. Sep 2023

    Ministry of Power

    National Framework for Promoting Energy Storage Systems

    Policy, regulatory and financial measures to deploy battery and pumped storage. Dated August 2023, released September 2023.

    What it changes: The umbrella policy behind later storage measures such as VGF, ISTS waivers and BESS procurement rules.

    StorageBatteriesGridpowermin.gov.inDetails
  6. Aug 2022

    MoEFCC

    Battery Waste Management Rules, 2022

    Extended producer responsibility for all battery types, including EV and industrial batteries: collection, recycling targets and minimum recycled content.

    What it changes: Battery makers and importers must register and meet EPR targets; end-of-life tracking matters.