Policy that moves solar & storage

Orders, rules and schemes from the Ministry of Power, MNRE and others, each with a line on what it changes for you. Always check the issuing body's site for the current text.

19 notifications · page 1 of 2

  1. Aug 2026

    CERC

    DSM (Third Amendment) Regulations, 2026: general-seller treatment for new RE

    Ends the softer deviation treatment for new wind and solar, and sets a rate for standalone storage's trial-run power. In force from 31 August 2026.

    What it changes: Solar and wind bid from 2027 face the same deviation charges as conventional plants, so storage and EMS-based schedule tracking become close to essential.

    StorageEMSSolarGridOfficial PDFDetails
  2. Aug 2026

    MNRE

    Rooftop solar inverter data and servers must stay in India

    Inverter makers in the rooftop solar scheme must keep monitoring servers, control servers and inverter data in India, citing cyber risk from data sent abroad.

    What it changes: Monitoring and remote-control platforms for rooftop inverters must be hosted in India, which sets the bar for any cloud EMS or remote monitoring on Indian solar.

    SolarEMSOfficial PDFDetails
  3. Jul 2026

    MNRE

    ALMM List-II: limited relief for net-metering and open-access projects

    Net-metering and open-access solar projects may be commissioned without List-II (domestic) cells until 31 December 2026.

    What it changes: Rooftop and C&I open-access projects get a short window before domestic cells become compulsory.

    SolarOpen accessOfficial PDFDetails
  4. Jun 2026

    CEA

    Construction standards for BESS and RE plants, with EMS requirements (2026)

    The CEA (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2026 add standards for solar, wind and BESS, including the first statutory specification for a BESS energy management system. In force from 1 April 2027.

    What it changes: From April 2027 every BESS needs an EMS with SCADA integration, remote set-points and 90-day high-resolution logging; 50 MW and above also needs AGC, grid-forming and black start.

    StorageEMSBatteriesGridSolarOfficial PDFDetails
  5. Mar 2026

    MNRE

    ALMM List-III for solar wafers

    A List-III for wafers is added to the ALMM Order. List-I modules must use List-II cells, which must use List-III wafers, from 1 June 2028.

    What it changes: From June 2028, ALMM-covered solar needs modules traced back to Indian wafers, which may affect module supply and price.

    Solarmnre.gov.inDetails
  6. Jun 2025

    CERC

    ISTS charges waiver phased out for RE; co-located BESS exempt to June 2028

    The CERC (Sharing of Inter-State Transmission Charges and Losses) (Fourth Amendment) Regulations, 2025 step down the waiver for new solar and wind after 30 June 2025. Storage charged from a co-located RE plant keeps a full waiver to June 2028.

    What it changes: ISTS solar and wind commissioned after June 2025 pay a rising share of transmission charges, while co-located BESS stays fully exempt until June 2028.

    StorageSolarGridOfficial PDFDetails
  7. Feb 2025

    Ministry of Power

    Advisory: 2-hour co-located storage with new solar tenders

    Implementing agencies and state utilities are advised to require co-located storage in future solar tenders: at least 2 hours, sized at 10% of solar capacity.

    What it changes: New solar tenders are expected to include 2-hour storage at 10% of plant capacity, so developers plan BESS from the start.

    StorageSolarpowermin.gov.inDetails
  8. Jan 2025

    MNRE

    Solar Systems, Devices and Components Goods Order, 2025

    Replaces the 2017 compulsory registration order. Solar modules, solar storage batteries and PV inverters must meet Indian Standards and carry the BIS mark.

    What it changes: Modules, inverters and solar storage batteries sold in India need a BIS licence, so check certification before buying.

    SolarBatteriesStorageOfficial PDFDetails
  9. Dec 2024

    MNRE

    ALMM List-II for solar PV cells

    A second Approved List of Models and Manufacturers, for cells. From 1 June 2026, modules on List-I used in eligible projects must use List-II cells.

    What it changes: Government-backed, net-metering and open-access projects move to modules made with Indian cells.

    SolarOfficial PDFDetails
  10. Aug 2024

    CERC

    Deviation Settlement Mechanism Regulations, 2024

    Charges for deviating from schedule in the inter-state grid, with separate rules for wind and solar, standalone storage and co-located storage. In force from 16 September 2024.

    What it changes: Tighter deviation bands for solar and wind make forecasting and EMS-driven storage dispatch worth money, and co-located storage is settled by operating mode.

    StorageEMSSolarGridOfficial PDFDetails