19 notifications · page 1 of 2
Aug 2026
CERC
Ends the softer deviation treatment for new wind and solar, and sets a rate for standalone storage's trial-run power. In force from 31 August 2026.
What it changes: Solar and wind bid from 2027 face the same deviation charges as conventional plants, so storage and EMS-based schedule tracking become close to essential.
Aug 2026
MNRE
Inverter makers in the rooftop solar scheme must keep monitoring servers, control servers and inverter data in India, citing cyber risk from data sent abroad.
What it changes: Monitoring and remote-control platforms for rooftop inverters must be hosted in India, which sets the bar for any cloud EMS or remote monitoring on Indian solar.
Jul 2026
MNRE
Net-metering and open-access solar projects may be commissioned without List-II (domestic) cells until 31 December 2026.
What it changes: Rooftop and C&I open-access projects get a short window before domestic cells become compulsory.
Jun 2026
CEA
The CEA (Technical Standards for Construction of Electrical Plants and Electric Lines) Amendment Regulations, 2026 add standards for solar, wind and BESS, including the first statutory specification for a BESS energy management system. In force from 1 April 2027.
What it changes: From April 2027 every BESS needs an EMS with SCADA integration, remote set-points and 90-day high-resolution logging; 50 MW and above also needs AGC, grid-forming and black start.
Mar 2026
MNRE
A List-III for wafers is added to the ALMM Order. List-I modules must use List-II cells, which must use List-III wafers, from 1 June 2028.
What it changes: From June 2028, ALMM-covered solar needs modules traced back to Indian wafers, which may affect module supply and price.
Jun 2025
CERC
The CERC (Sharing of Inter-State Transmission Charges and Losses) (Fourth Amendment) Regulations, 2025 step down the waiver for new solar and wind after 30 June 2025. Storage charged from a co-located RE plant keeps a full waiver to June 2028.
What it changes: ISTS solar and wind commissioned after June 2025 pay a rising share of transmission charges, while co-located BESS stays fully exempt until June 2028.
Feb 2025
Ministry of Power
Implementing agencies and state utilities are advised to require co-located storage in future solar tenders: at least 2 hours, sized at 10% of solar capacity.
What it changes: New solar tenders are expected to include 2-hour storage at 10% of plant capacity, so developers plan BESS from the start.
Jan 2025
MNRE
Replaces the 2017 compulsory registration order. Solar modules, solar storage batteries and PV inverters must meet Indian Standards and carry the BIS mark.
What it changes: Modules, inverters and solar storage batteries sold in India need a BIS licence, so check certification before buying.
Dec 2024
MNRE
A second Approved List of Models and Manufacturers, for cells. From 1 June 2026, modules on List-I used in eligible projects must use List-II cells.
What it changes: Government-backed, net-metering and open-access projects move to modules made with Indian cells.
Aug 2024
CERC
Charges for deviating from schedule in the inter-state grid, with separate rules for wind and solar, standalone storage and co-located storage. In force from 16 September 2024.
What it changes: Tighter deviation bands for solar and wind make forecasting and EMS-driven storage dispatch worth money, and co-located storage is settled by operating mode.