Policy that moves solar & storage

Orders, rules and schemes from the Ministry of Power, MNRE and others, each with a line on what it changes for you. Always check the issuing body's site for the current text.

19 notifications · page 2 of 2

  1. Feb 2024

    Ministry of Power

    Electricity (Rights of Consumers) Amendment Rules, 2024: faster rooftop solar

    Rooftop solar up to 10 kW no longer needs a technical feasibility study, and larger systems get shorter discom deadlines.

    What it changes: Rooftop solar applicants get faster approvals and fixed discom deadlines; complete applications up to 10 kW are deemed accepted.

    SolarGridOfficial PDFDetails
  2. Feb 2024

    Union Cabinet / MNRE

    PM Surya Ghar: Muft Bijli Yojana

    Central subsidy for rooftop solar on one crore homes, with up to 300 units a month of free electricity.

    What it changes: Home rooftop solar demand rises; home batteries and inverter EMS follow.

    SolarOfficial PDFDetails
  3. Jun 2023

    Ministry of Power

    Carbon Credit Trading Scheme, 2023

    Sets up the Indian carbon market under the Energy Conservation Act, 2001. Notified obligated entities get greenhouse-gas targets; others may buy certificates voluntarily.

    What it changes: Plants with emission-intensity targets can use solar and storage to cut emissions instead of buying carbon credits.

    SolarOfficial PDFDetails
  4. Jun 2023

    Ministry of Power

    Time-of-Day tariff: Electricity (Rights of Consumers) Amendment Rules, 2023

    Makes Time-of-Day tariffs compulsory. C&I consumers above 10 kW maximum demand move to ToD tariffs no later than 1 April 2024.

    What it changes: Peak rates at least 20% above normal and solar-hour rates at least 20% below give C&I sites a clear gap for EMS-scheduled battery charging and peak shaving.

    StorageEMSSolarpib.gov.inDetails
  5. May 2023

    Ministry of Power

    Green Energy Open Access (Second Amendment) Rules, 2023

    Consumers can add up several connections to reach the 100 kW threshold for green open access. Captive consumers have no load limit.

    What it changes: C&I sites with several smaller connections in one discom division can combine them to qualify for green open access.

    Open accessSolarOfficial PDFDetails
  6. May 2023

    CERC

    Indian Electricity Grid Code, 2023

    A new grid code for planning, connection, commissioning, scheduling and operation, treating energy storage as its own class of grid user. In force from 1 October 2023.

    What it changes: Commissioning a storage or RE plant depends on working plant controllers, telemetry and active-power control, all delivered through the EMS.

    StorageEMSSolarGridOfficial PDFDetails
  7. Jun 2022

    Ministry of Power

    Green Energy Open Access Rules, 2022

    Lowers the open-access threshold to 100 kW, sets time-bound approvals and caps additional charges for green power.

    What it changes: Mid-sized C&I sites can buy renewable power through open access; storage firms up the supply.

    Open accessSolarOfficial PDFDetails
  8. May 2022

    CERC

    Renewable Energy Certificate Regulations, 2022

    Resets the REC system: one certificate per MWh of renewable power. In force from 5 December 2022.

    What it changes: Captive solar owners and open-access buyers beyond their obligation can get RECs, but certificates for self-consumed power cannot be sold.

    SolarOpen accessOfficial PDFDetails
  9. Jan 2019

    MNRE

    ALMM Order, 2019: approved list of solar modules (List-I)

    Sets up the Approved List of Models and Manufacturers. Covered projects may only use enlisted modules. Held in abeyance for FY 2023-24 and applied again from 1 April 2024.

    What it changes: Net-metering and open-access solar must use ALMM List-I modules, which narrows module choice and affects cost.

    SolarOpen accessOfficial PDFDetails