19 notifications · page 2 of 2
Feb 2024
Ministry of Power
Rooftop solar up to 10 kW no longer needs a technical feasibility study, and larger systems get shorter discom deadlines.
What it changes: Rooftop solar applicants get faster approvals and fixed discom deadlines; complete applications up to 10 kW are deemed accepted.
Feb 2024
Union Cabinet / MNRE
Central subsidy for rooftop solar on one crore homes, with up to 300 units a month of free electricity.
What it changes: Home rooftop solar demand rises; home batteries and inverter EMS follow.
Jun 2023
Ministry of Power
Sets up the Indian carbon market under the Energy Conservation Act, 2001. Notified obligated entities get greenhouse-gas targets; others may buy certificates voluntarily.
What it changes: Plants with emission-intensity targets can use solar and storage to cut emissions instead of buying carbon credits.
Jun 2023
Ministry of Power
Makes Time-of-Day tariffs compulsory. C&I consumers above 10 kW maximum demand move to ToD tariffs no later than 1 April 2024.
What it changes: Peak rates at least 20% above normal and solar-hour rates at least 20% below give C&I sites a clear gap for EMS-scheduled battery charging and peak shaving.
May 2023
Ministry of Power
Consumers can add up several connections to reach the 100 kW threshold for green open access. Captive consumers have no load limit.
What it changes: C&I sites with several smaller connections in one discom division can combine them to qualify for green open access.
May 2023
CERC
A new grid code for planning, connection, commissioning, scheduling and operation, treating energy storage as its own class of grid user. In force from 1 October 2023.
What it changes: Commissioning a storage or RE plant depends on working plant controllers, telemetry and active-power control, all delivered through the EMS.
Jun 2022
Ministry of Power
Lowers the open-access threshold to 100 kW, sets time-bound approvals and caps additional charges for green power.
What it changes: Mid-sized C&I sites can buy renewable power through open access; storage firms up the supply.
May 2022
CERC
Resets the REC system: one certificate per MWh of renewable power. In force from 5 December 2022.
What it changes: Captive solar owners and open-access buyers beyond their obligation can get RECs, but certificates for self-consumed power cannot be sold.
Jan 2019
MNRE
Sets up the Approved List of Models and Manufacturers. Covered projects may only use enlisted modules. Held in abeyance for FY 2023-24 and applied again from 1 April 2024.
What it changes: Net-metering and open-access solar must use ALMM List-I modules, which narrows module choice and affects cost.