DG chalane wali factory ke liye battery: kaunsi line us par daalein, aur kitna bachega
Yeh page lagbhag 50 kW se 1 MW ki factory ke malik ya plant head ke liye hai, jahan transformer, PCC aur MCC panel, AMF panel aur DG set hai jo light jaate hi chalta hai. Hum aapke shop floor ko feeder-by-feeder dekhte hain: light jaane par har line ka kya hota hai, battery kya utha sakti hai, motor kaise start hogi, DG ke naye niyam kya maangte hain, aur diesel ka hisaab kya banta hai.
16 November 2026 ko Ingro Energy ki project team ne check kiya
Seedha jawab
- Moulding, extrusion, spinning ya process line par light jaane ka asli nuksaan aksar diesel nahi, line ko dobara chalu karna hai. Hyderabad ke industrial area ke udyogpatiyon ne October 2026 mein kaha ki 30 minute ke cut ke baad bhi kaam normal hone mein lagbhag teen ghante lagte hain. Battery in line ko cut ke beech chalati rahe to restart hi nahi karna padta; DG yeh kabhi nahi kar sakta, kyunki woh light jaane ke baad hi start hota hai.
- Zyaadatar factory battery par sirf woh line daalti hain jo rukne par maal scrap karti hain, saath mein PLC, chiller aur air compressor; furnace aur doosre bhaari load DG par rehte hain. Yahi faisla size aur keemat tay karta hai.
- Battery ka inverter aapki sabse badi motor ke starting current ke hisaab se chuna jaata hai, running load se nahi. Aapka DG iske liye ek niyam maanta hai; battery ka apna hisaab chahiye.
- DG ki ek unit sirf diesel mein lagbhag ₹30 ki; grid se charge hui battery ki unit lagbhag ₹11 ki. DG rakhiye, lambe cut aur bhaari load ke liye.
- Delhi-NCR mein, aur July 2026 se Gujarat ke non-attainment shehron mein, purane diesel set ko dual fuel par badalna ya emission control device lagana zaroori hai. Agar aapke set par yeh kharcha aana hi hai, to saath mein battery ka bhi daam nikalwa lijiye.
DG aane tak ka gap har line ke saath kya karta hai
Cut sirf garmi ki baat nahi: October 2026 mein power plant par coal kam hone se, Business Today ne Chhattisgarh ki chhoti steel mill mein roz 10 se 12 ghante aur Ludhiana ki ek wire factory mein 3 se 4 ghante ke cut report kiye. Light jaane par AMF panel pehle pakka karta hai ki supply sach mein gayi hai, phir engine crank karta hai, voltage aur frequency set hone ka intezaar karta hai, aur tab DG ka breaker lagata hai. Ismein kuch second lagte hain. Machine isse kahin pehle react karti hai: Fuji Electric India ki plastic processing guide ke hisaab se voltage 80% se neeche 20 millisecond (supply ka ek cycle) se zyada gire to machine bigadne lagti hai. Contactor gir jaate hain, drive trip ho jaati hain, aur saari line ek saath beech cycle mein ruk jaati hai, bina kisi theek shutdown ke.
- Injection moulding: press bhare barrel aur garam hot runner ke saath ruk jaati hai, sahi shutdown ka bilkul ulta. Canadian Plastics ki shutdown guide kehti hai ki nylon, acetal aur PVC aise chhodne par degrade ho sakte hain aur purging chahiye, clear polycarbonate garmi mein pada rahe to bada scrap ho sakta hai, aur bhara barrel thanda hone par screw par bina pighla maal lipat sakta hai.
- Extrusion: melt die mein hi ruk jaata hai. EC&M mein ek plant ki kahani hai jahan voltage sag par drive trip hui aur pighla polymer die aur roller mein chipak gaya; drive theek karne se pehle chhe mahine mein lagbhag 35 baar production ruka.
- Roving aur spinning: Textile Network batata hai ki roving frame ki light jaane par drive bina control ke rukti hai, 300 tak spool par roving toot jaati hai, aur staff ko haath se dobara dhaaga chadhana padta hai; ek outage mein kai machine par ghanton ka nuksaan.
- Garam ya lagataar chalne wali process line (dryer, boiler, oven, roaster): Telangana Today ki October 2026 report mein udyogpati kehte hain ki chhote cut ke baad bhi machine aur boiler ko kaam laayak hone mein ghante lagte hain, aur tab tak shift khaali baithi rehti hai.
- CNC aur doosri batch machine: beech cut mein ruka job scrap ho sakta hai, aur machine ko dobara reference karna padta hai.
In mein se koi nuksaan diesel ke bill mein nahi dikhta, isliye khud giniye: har cut mein kitna maal scrap, line ko achhe part tak laane mein kitne ghante, aur mahine mein kitne cut chalti shift mein aate hain.
Panel room mein battery kahan lagti hai
Is size ke plant mein supply HT ya LT par aati hai, transformer se main PCC tak, aur wahan se floor ke MCC aur DB tak. DG AMF changeover se PCC ko feed karta hai. Battery system (battery, uska inverter jise PCS kehte hain, aur uska panel) aam taur par LT side par judta hai: ya to PCC par, apni rating tak sab kuch uthane ke liye, ya ek alag critical-load bus par jo sirf chune hue MCC ko feed kare.
Do cheezein aapka electrical contractor dekhega. Kai DISCOM consumer se likhwa lete hain ki DG unki supply ke saath parallel nahi chalega, isliye grid, battery aur DG ke beech changeover aisa banta hai ki kahin se bhi back-feed na ho. Aur aapka APFC capacitor bank: jab load battery ya DG par hota hai to capacitor stage aur power factor badal jaate hain, isliye setting teeno source ke liye ki jaati hai, sirf grid ke liye nahi.
Aapka shop floor kaun chala raha hai, minute-dar-minute
Bhari line woh hai jo zaroori line ko chala rahi hai. Dotted line AMF panel par intezaar karta DG hai.
Motor starting: DG ka niyam, aur battery ka
Bureau of Energy Efficiency (BEE) ki DG set guide saaf kehti hai: DOL starter se chalne wali squirrel-cage motor kuch second ke liye apne rated current ka chhe guna tak kheenchti hai. Aam niyam hai ki DG DOL par apne kVA ke lagbhag 50% HP tak ki sabse badi motor start kar sakta hai; star-delta ya auto-transformer starter ho to 75% tak. Guide yeh bhi kehti hai ki sabse zyada starting kVA wala load pehle chalaiye, baaki ghatte kram mein.
Battery inverter ki apni chhoti overload rating hoti hai, jo uske electronics se tay hoti hai; BEE ke hisaab se alternator 15 second ke liye 50% overload ke liye bana hota hai, to PCS ki datasheet se yeh milaiye. PCS aapki sabse badi motor ke starting kVA aur us waqt chal rahe baaki load se chuna jaata hai, running load se nahi. Compressor, pump aur blower par VFD ya soft starter starting kVA bahut kam kar deta hai, aur panel mein start sequence do badi motor ko ek saath start nahi hone deta. Welding set, induction ya thyristor wale furnace aur bade rectifier ka alag application check chahiye, battery ke liye bhi aur DG ke liye bhi.
Har vendor se poochhiye: "Yeh system battery par sabse badi kaunsi motor start karega, kis starter ke saath, aur saath mein kya chal raha hoga?" Likhit mein lijiye, aur testing par chala kar dekhiye.
Battery par kaunse feeder jaayein
Apne MCC par ek-ek feeder ke liye poochhiye: "is par light jaane ka kharcha kya hai?" Aam taur par baatwara kuch aisa hota hai; aakhri faisla aapki line karegi.
| Feeder | Cut ka nuksaan | Aam taur par |
|---|---|---|
| Moulding machine, extruder, roving aur spinning frame, process line | Scrap, purging, dhaaga chadhana, restart mein ghante | Battery |
| PLC, SCADA, instrument, server | Recipe aur setting gum, dheema restart | Battery |
| Mould aur process chiller, air compressor | Inke bina line chalu hi nahi hoti | Battery, VFD ya soft starter ke saath |
| Lighting, office, canteen | Kam | Jagah ho to battery, warna DG |
| Bade furnace, heater, oven, bhaari welding | Garmi dheere jaati hai; load bahut bada | DG |
| Pump, crane, conveyor jo ruk sakte hain | Kuch minute ki deri | DG |
Battery par sirf upar ki teen line daalne se kWh aur daam theek rehte hain. Neeche ka udaharan yahi fark dikhata hai.
DG asal mein kitne ka padta hai
Theek load par DG ek litre diesel se lagbhag 3.2 unit banata hai, to ₹95 litre par DG ki unit lagbhag ₹30 ki padti hai. Grid se charge hui battery jitna leti hai uska lagbhag 85% wapas deti hai, to ₹9 ki grid unit par battery ki unit lagbhag ₹11 ki. Brochure se achha aapka apna figure hai: BEE guide mein steady load par do ghante ka trial bataya gaya hai, jismein diesel dip se aur unit DG ke kWh meter se note karke apne set ki asli unit prati litre nikalte hain.
Hisaab mein do cheezein aur judti hain. BEE kehta hai ki engine load 50% se upar rakhna chahiye; chhote cut mein halke load par chalta DG prati unit sabse zyada diesel jalata hai. Aur hour meter: isi guide ke hisaab se high-speed engine mein do overhaul ke beech aam taur par lagbhag 3,200 ghante hote hain, to DG jitne ghante kam chale, agla overhaul utna door.
| Unit kahan se aayi | Prati unit kharcha |
|---|---|
| DG set (sirf diesel) | lagbhag ₹30 |
| Battery, grid se charge | lagbhag ₹11 |
| Battery, chhat ke solar se charge | aur bhi kam |
Agar aap diesel pump se nahi, oil company se bulk mein lete hain, to neeche apna daam daaliye. June 2026 mein petroleum mantralaya ne kaha tha ki retail diesel bulk se lagbhag ₹40 litre sasta hai.
Apne diesel se hisaab lagaiye
Aapki DG log book ke chaar number. Jab tak aap check karne na kahein, kuch kahin nahi jaata.
Hisaab dekhne ke liye diesel ke litre aur DG ke ghante daaliye.
Hisaab kaise lagaya
- DG ek litre diesel se lagbhag 3.2 unit banata hai; halke load par kam banata hai, jisse battery aur achhi dikhti hai.
- Grid ki unit lagbhag ₹9, aur battery jitna leti hai uska lagbhag 85% wapas deti hai.
- Battery ek normal din ke DG chalne jitni ek charge mein rakhi hai. Sirf zaroori line rakhne se chhoti hogi.
- Kharcha 250 kWh se chhoti battery ke liye ₹25,000 se ₹38,000 prati kWh, aur badi ke liye ₹20,000 se ₹30,000 prati kWh, GST se pehle. Yeh andaaza hai, quotation nahi.
- Scrap aur restart ka samay, DG ka taala hua overhaul, bacha hua retrofit kit aur solar gine nahi gaye.
- Yeh pehla andaaza hai. Motor starting, aapke feeder aur tariff daam batane se pehle check hote hain.
Apne plant ka figure lijiye
Naam aur number chhodiye. Hum feeder, size, kharcha aur paisa wasool ke saath call karenge.
Apne plant ke baare mein bataiye ↓Udaharan: poora load, ya sirf zaroori line
Yeh samjhane ke liye udaharan hai, kisi asli factory ka nahi. Maan lijiye: do shift ka plant, jiska DG kaam ke din lagbhag 2 ghante ke cut mein lagbhag 160 kW uthata hai, saal bhar, aur mahine mein lagbhag 3,000 litre diesel jalata hai (₹95 par mahine ka lagbhag ₹2.9 lakh). Calculator wale hi hisaab se:
| A: poora chalta load | B: sirf zaroori line | |
|---|---|---|
| Battery par load | lagbhag 160 kW | lagbhag 90 kW |
| Ek din ke cut ke liye battery | lagbhag 360 kWh | lagbhag 205 kWh |
| Saal ka diesel bacha | lagbhag ₹22 lakh | lagbhag ₹12 lakh |
| Lagaane ka kharcha, GST se pehle | ₹72 se 108 lakh | ₹51 se 78 lakh |
| Sirf diesel se paisa wasool | 3.3 se 4.9 saal | 4.1 se 6.2 saal |
B mein diesel kam bachta hai, aur chhoti battery prati kWh mehngi padti hai, to sirf diesel se iska paisa jaldi wasool nahi hota. Phir bhi aksar yahi chuna jaata hai, kyunki yeh zaroori line ka scrap aur restart bachata hai, jo is table mein gina hi nahi. Agar woh aapke liye bada nuksaan hai to B sahi hai; agar dikkat sirf diesel ke bill ki hai, to A ka hisaab hi seedha hai.
DG ke niyam jo faisla kar sakte hain
- Delhi-NCR: Commission for Air Quality Management (CAQM) ka schedule 1 October 2023 se laagu hai. Industry ke purane diesel DG set ko, size ke hisaab se, dual fuel (gas aur diesel) par chalana hai ya certified retrofit emission control device lagana hai. June 2023 ke schedule mein GRAP ke dauran kuch size ke set din mein do ghante tak seemit the; size ki category 2024 mein badli gayi.
- 800 kW tak ke naye set jo 3 November 2022 ko notify hue emission limit (CPCB IV+, 1 July 2023 se laagu) par bane hain, unhe us schedule mein retrofit nahi chahiye.
- 28 September 2026 ke naye GRAP mein CAQM ne DG set wale kadam Stage II se Stage I mein daal diye, yaani sardi mein hawa kharab hote hi pehle stage se laagu.
- Gujarat: GPCB ka 7 July 2026 ka circular yahi CAQM direction rajya ke non-attainment shehron ke DG set par laagu karta hai, inspection aur consent to operate ke renewal par check hota hai.
- Diesel ki supply bhi: 12 June se 1 July 2026 tak sarkar ne industrial kharidaron ko retail pump se diesel lene se roka aur pump par 200 litre roz ki seema lagayi. DG utna hi bharosemand hai jitni uski diesel supply.
Yeh schedule DG set ke baare mein hain; battery koi fuel nahi jalati aur uska dhuan nahi hota. Agar niyam mein rehne ke liye aapke set par retrofit kit ya naya set lagna hai, to faisle se pehle woh kharcha battery ke daam ke saath rakh kar dekhiye.
DG rehta hai, aur behtar chalta hai
Har cut aur poore plant ke liye battery bahut mehngi padegi, isliye DG lambe cut aur bhaari load ke liye rehta hai. Phir woh kam baar start hota hai, aur jab chalta hai to zyada aur steady load par, jaisa BEE kehta hai. Battery aur DG ki poori tulna ke liye neeche wali guide dekhiye.
Factory yeh karne lagi hain. February 2026 mein Greater Noida ki CMIL, jo malted drink aur cereal banati hai, ne apne plant mein 2 MWh battery ka elaan kiya; wajah batayi roz 2 se 3 ghante ke cut aur spray-drying, extrusion aur roasting line jinhe bina ruke bijli chahiye.
Daam, battery ki umar aur solar, chhote mein
Lagi hui system lagbhag ₹20,000 se ₹35,000 prati kWh padti hai, GST se pehle; chhoti system prati kWh mehngi. Daam kis se badalta hai, yeh battery cost guide mein hai. Ek turnkey daam maangiye jismein PCS, panel, cabling, civil kaam aur testing sab ho.
Cell lithium iron phosphate (LFP) ke hote hain; warranty saal, cycle aur aakhir mein bachi capacity, teeno mein padhiye, aur cabinet ko furnace, compressor ke exhaust aur dhool se door rakhiye.
Agar shed ki chhat par solar hai ya jagah hai, to factories with solar guide dekhiye; agar bill ka demand charge dikkat hai, to commercial buildings guide.
Factory mein battery kab nahi leni chahiye
- Cut zyaadatar raat ko ya weekly off par aate hain, jab line band hoti hai. Na restart bachana hai, na zyada diesel.
- Aapki line minute-do minute mein saaf chalu ho jaati hai aur kuch scrap nahi hota: ruka lathe ya press brake kam nuksaan karta hai. Tab sirf diesel ka hisaab bachta hai, aur woh shayad kaafi na ho.
- Cut mein aapka load zyaadatar ek bhaari furnace ya heater bank hai jo DG par hi rahega. Baaki ke liye battery se diesel kam bachega.
- Cut aadhi shift se lambe hain aur plant chaubees ghante chalta hai. Recharge ke liye grid ke ghante kam hain, DG to chalega hi.
- Aapka DG naya hai, pehle se CPCB IV+ hai, aur mahine mein kuch ghante chalta hai. Na niyam, na diesel, koi wajah nahi deta.
Agar asli dikkat lambe cut nahi, balki kuch machine ka dip par trip hona hai, to bataiye: un feeder ke liye chhoti battery ya power-quality ka hal hi seedha jawab ho sakta hai.
Sign karne se pehle kya poochhein
- Kaunse feeder aur MCC isse chalenge, kitne kW, aur kitne ghante?
- Line chalte hue light jaaye to kya woh bina ruke chalengi? Kya testing par mere chalte load par dikhayenge?
- Battery par sabse badi kaunsi motor start hogi, kis starter ke saath aur saath mein kya chal raha hoga?
- Grid, battery aur DG ka changeover kaise interlock hai, taaki kuch bhi grid ke saath parallel na chale?
- Kya mere APFC ki setting badlegi, aur kaun karega?
- Kya daam mein panel, cabling, civil kaam aur zaroori approval shaamil hain?
- Warranty kitne saal aur cycle ki, aur aakhir mein kitni capacity ka vaada?
- Shift ke beech trip ho jaaye to kaun aayega, aur kitni der mein?
Equipment aur judi hui guide
- India mein bikne wale BESS cabinet, specification ke saath
- BESS container, bade plant ke liye
- PCS (battery inverter): overload rating dekhiye
- DG set, tulna ke liye
- Power-quality equipment, dip par trip hone wali line ke liye
- Battery ya diesel generator: poori tulna
- India mein battery system ka kharcha
- Chhat par solar wali factory: bekaar jaati unit ka istemaal
- Bill ka demand charge: commercial buildings
- Ingro battery site shuru se aakhir tak kaise banata hai
Plant head jo poochhte hain
Kya battery par meri moulding machine aur extruder cut mein bina ruke chalenge?
Chal sakte hain, agar woh battery ke bus par hain aur system aise set hai ki machine ko break mehsoos na ho. Kitna smooth hoga yeh PCC ki wiring par depend karta hai, isliye testing par line chalte hue grid band karke dikhane ko kahiye.
Kya battery mere DG ke saath chal sakti hai?
Haan, alag-alag source ki tarah, interlock wale changeover ke saath: battery critical bus chalati hai, DG lambe cut ya bhaari load ke liye start hota hai. Kai DISCOM likhwate hain ki DG unki supply ke saath parallel nahi chalega, isliye scheme aisi banti hai ki grid mein kuch back-feed na ho.
Kya battery mera air compressor ya 50 HP ki motor start karegi?
Haan, agar PCS us motor ke starting kVA aur baaki chalte load ke hisaab se chuna gaya ho. DOL motor start hote waqt rated current ka chhe guna tak kheenchti hai, isliye VFD ya soft starter se battery kaafi chhoti aur sasti ho jaati hai.
Meri factory NCR mein hai. Kya battery CAQM ke DG niyam mein madad karti hai?
CAQM ka schedule DG set ke liye hai: purane diesel set ko dual fuel ya retrofit emission control device chahiye. Battery koi fuel nahi jalati. Agar aapke set par yeh kaam hona hai, to uska kharcha us battery se milaiye jo DG ka chalna hi kam kar de.
Supply HT hai ya LT, kya fark padta hai?
Battery ke liye zyada nahi; woh aam taur par transformer ke baad LT side par, PCC ya critical-load bus par judti hai. Supply ke type se woh tariff badalta hai jis par battery charge hoti hai, aur approval bhi, jo engineer check karta hai.
Factory ko kitni badi battery chahiye?
Apni DG log book se shuru kijiye: normal kaam ke din DG jitni unit banata hai, lagbhag utne kWh battery mein chahiye, wahi load uthane ke liye. Sirf zaroori line rakhne se yeh kam ho jaata hai.
Sources
- Bureau of Energy Efficiency, energy auditor guide book 3, chapter 9: DG Set System (motor starting, loading, parallel operation, performance trial)
- Fuji Electric India, technical guide: reliable power for the plastic processing industry (voltage dip threshold)
- Canadian Plastics, Technical tip: the fundamentals of press shutdown
- EC&M, Don't let sags and interruptions disturb you (extrusion plant case)
- Textile Network, 3 December 2019: power failure on roving frames
- Telangana Today, 18 October 2026: unscheduled power cuts worry Hyderabad industries
- EQ Mag Pro, 8 June 2023: CAQM revised schedule for DG sets in NCR from 1 October 2023
- TeamLease RegTech: CAQM amendment to DG set capacity bands (2024)
- SCC Online, 7 November 2022: Environment (Protection) Third Amendment Rules 2022, genset engines up to 800 kW
- ThePrint, 29 September 2026: CAQM revises GRAP, DG set actions moved to Stage I
- Corpseed, 22 July 2026: GPCB circular on DG set emission control in Gujarat
- Business Today, 12 June 2026: diesel sales capped at 200 litres; retail about ₹40 a litre cheaper than bulk
- Business Today, 13 October 2026: coal crisis, factories face 12-hour power cuts
- SolarQuarter, 13 February 2026: GoodEnough Energy and CMIL, 2 MWh battery for a Greater Noida food plant
- The Tribune, 29 June 2026: retail diesel restrictions lifted from 1 July
In sites ko battery storage se fayda hua
Alag-alag sites, ek hi baat: apni solar aur green bijli zyada istemaal kijiye, bijli ka bill ghataiye, aur grid saath na de tab bhi kaam chalta rahe.
LiveAPAR Industries · Factory · 720 kW / 500 kWh batteryA factory whose process lines keep running through every dip in power.
- <1 ms
- response when the load jumps or the grid dips
- Zero
- gaps in power to the production lines
- End to end
- battery, PCS, controls and installation by one team
LiveEV charging hub · 260 kW / 580 kWh battery · IndiaElectric buses and cars keep charging, even when the grid is gone.
- 2.5×
- charging power from the same grid connection
- 1 s
- battery and PCS data, cell by cell
- Grid outage
- buses and cars still charge off the battery
UnderwaySolar + battery micro-grid · Melghat, MaharashtraA village without a grid. A solar and battery micro-grid that powers it.
- Village
- no grid connection
- Black start
- from standstill, no outside source
- 820
- homes on solar and battery
In testingIndustrial battery plant · Pune · 2.5 MW / 10 MWhTwo battery containers, two vendors, two languages. One EMS runs them as one plant.
- 2
- container makes, each with its own BMS protocol
- 1
- PCS and one EMS across both
- Hot-swap
- take a container out for service, plant keeps running
Apne plant ke baare mein bataiye
Jo pata hai bhejiye. Ingro ka engineer muft mein nikalega ki battery par kaunse feeder jaayein, size, kharcha aur paisa wasool.
Aage kya hoga: hum ek working day ke andar phone ya WhatsApp par jawab denge. Abhi site visit ki zaroorat nahi, aur koi paisa nahi lagta.