Rice ya atta mill par solar, zero export se ruka hua: units kahan jaati hain, aur battery ka hisaab banta hai ya nahi
Godown aur mill shed par 100 se 500 kWp ke panel lag gaye. Saaf dhoop wale din inverter app mein graph flat ho jata hai jaise hi lunch par huller line rukti hai, polisher dhaan ka intezaar karta hai ya shift badalti hai. Season ke baad mill band, aur panel kuch kaam ka nahi banate. Yeh page rice mill ya roller flour / atta mill ke malik aur partners ke liye hai, LT ya HT industrial connection, munim ke haath mein bill. Yeh batata hai ki aapka solar kahan jaata hai, aapke state ke rules kya allow karte hain, battery se pehle kaunse saste upay try karein, aur battery kab theek hai aur kab nahi.
16 November 2026 ko Ingro Energy ki project team ne check kiya
Seedha jawab
- Zero export par, jo unit mill us waqt use nahi kar paati, inverter use phenk deta hai. Mill mein yeh hota hai lunch break par, shift change par, jab line dhaan ya gehun ke liye rukti hai, weekly off par, aur rice ke off-season mein poore mahino tak.
- Battery mein rakhi aur wapas di har solar unit ₹9 ke grid rate par lagbhag ₹7.7 bachati hai. Neeche ke example mein, 300 kWp ka plant aur saal bhar chalne wali mill, payback lagbhag 9.5 se 14 saal. Wahi rice mill agar saal mein 6 mahine chale: lagbhag 19 se 29 saal.
- Isliye zyada tar mills ke liye pehla kadam battery nahi hai. Pehle export allow karwaiye (net metering ya zyada export limit), aur colour sorter, grading aur pump jaise load solar ke ghanton mein le aaiye.
- Battery tab theek lagti hai jab export mana ho ya cap ho, mill saal ke zyada mahine chalti ho, aur rakhi units use karne ke liye shaam ya raat ki shift ho, ya din ke regular cut hon jinme abhi DG chalta hai.
Dopahar ko aapka solar kahan jaata hai, mill ki bhasha mein
Mill ka load ek jaisa nahi rehta. Dhaan aa raha ho to huller, polisher, whitener aur elevator ki motor saath chalti hain, aur na aaye to saath rukti hain. Colour sorter, grader aur aspirator fan line ke saath chalte hain. Roller flour mill mein roller mill, plansifter aur pneumatic conveying shift mein chalte hain. Udhar solar dheere dheere badh kar dopahar ko peak par jaata hai. Jab bhi load panel ki bijli se neeche girta hai, zero-export controller inverter ko kaat deta hai, aur woh solar gaya.
| Mill mein kya hota hai | Solar par kya asar |
|---|---|
| Lunch break, 1 baje line band | Load theek peak dhoop par girta hai; us ghante graph flat |
| Shift change ya safai ke liye stop | Chhota sa dip, har working day |
| Huller ya polisher dhaan ke intezaar mein, ya breakdown | Kabhi bhi dip; jis din dhaan kam aaye us din sabse zyada |
| Weekly off ya mandi ki chhutti | Lagbhag poore din ka solar kata, hafte mein ek baar |
| Rice ka off-season, mill band | Mahino tak lagbhag saari bijli kati, raat ko bhi koi load nahi |
| Flour mill, seedhi shift | Roz chhote dip; surplus zyada tar break aur chhutti ke din |
Yeh sab bijli ke bill mein kahin nahi dikhta, isliye malik log chaunk jaate hain. Saaf dhoop wale milling day aur band din par inverter app kholiye, aur dono graph ko panel ki rated output se milaiye.
Mill zero export par kyun aa jaati hai
Solar export karne ke liye DISCOM ki approval chahiye, aur rules usme limit lagate hain. Kendra ke Electricity (Rights of Consumers) Amendment Rules, 2021 mein net metering 500 kW ya sanctioned load, jo bhi kam ho, tak ke load ke liye hai, aur 500 kW se upar gross metering; baaki details har state ke regulations tay karte hain. Mill wale details mein hi atakte hain: sanctioned load ke hisse ke roop mein plant size ki limit, ek distribution transformer par kitna solar lag sakta hai uski limit, ya aisi category jise net metering milti hi nahi.
Jab plant state ki limit se bada ho, transformer bhara ho, ya file atki ho, to kai plant behind the meter, bina export ke, jod diye jaate hain. Incomer par ek meter power flow dekhta hai aur jab mill panel se kam bijli le, controller inverter ko daba deta hai. Punjab ke 2026 amendment mein, trade report ke mutabik, behind-the-meter plant ke liye pehle approval chahiye aur jo units bahar nikal jaayein unka na paisa milta hai na adjustment.
March 2026 mein Ministry of Power ne in kendriya rules ka ek draft amendment nikala, jisme states 500 kW se bade plant par energy storage zaroori kar sakte hain. Yeh page check hone tak yeh draft hi tha; notify hua ya nahi, dekh lijiye.
Punjab, Uttar Pradesh aur Chhattisgarh kya allow karte hain: kuch example
Yeh example seedhe regulations se ya unki trade reports se hain, saal ke saath. Rules state ke hisaab se aur plant kab juda uske hisaab se alag hain, aur aksar badalte hain. Asli baat aapka connection agreement aur DISCOM ke abhi ke regulations hain.
| State aur rule | Kya kehta hai | Mill ke liye matlab |
|---|---|---|
| Punjab, PSERC rooftop regulations, 2021 | Non-domestic consumer ka plant (inverter ki AC rating) sanctioned load ya contract demand ke 70% se zyada nahi (kVA ko 0.9 power factor par). Net metering 500 kWp tak. Ek distribution transformer ya feeder par saare rooftop plant uski rating ke 80% tak. | 300 kW sanctioned load wali mill is rule mein zyada se zyada 210 kW inverter net meter kar sakti thi; bada plant zero export par jayega ya load badhwana padega |
| Punjab, 2021, net metering settlement | Surplus settlement period ke andar aage carry hota hai. Saal ki khapat ke 90% se upar ki generation ka paisa nahi, lapse. ToD mein ek time block ka extra agle saste block mein adjust. | Net metering ke saath bhi, jo mill saal mein lagbhag utna banaye jitna khaaye, saal ke end mein units kho sakti hai |
| Punjab, 1st amendment, 2024 | Rice sheller, rice bran stabilisation unit aur cotton ginning, jo tariff mein seasonal industry hain, ka settlement 1 April se 31 March, October-September nahi. | April se bank hui off-season units October se March ke milling mahino mein use ho sakti hain, reset se pehle |
| Punjab, 2nd amendment, 2025 | Plant ke liye transformer ya service line upgrade karni ho to DISCOM karega aur kharcha uske revenue requirement mein jayega. | Bhara transformer akele mana karne ki wajah nahi; upgrade maangiye |
| Punjab, 3rd amendment, 2026 (trade report) | Net metering sanctioned load ya contract demand se judi, 500 kWp ki ceiling. Saal ke end ka bacha net metering credit feed-in tariff ke 75% par. Behind-the-meter ke liye pehle approval; bahar nikli units ka paisa nahi. | Plan se pehle dekhiye ki aapke connection ki date par kaunsa version lagta hai |
| Uttar Pradesh, UPERC rooftop regulations, 2019 | Net metering metered residential aur agricultural consumer ke liye; baaki gross metering par, jisme saari bijli export hoti hai aur bade solar tariff se judi rate milti hai. Plant contracted demand ke 100% tak; transformer ke 75% tak. | In rules mein industrial mill net metering se apna bill kam nahi kar sakti thi; dekhiye ki baad ke amendment mein aapki category aayi ya nahi |
| Chhattisgarh, CSERC regulations, 2019 | Koi bhi consumer net metering le sakta hai, plant sanctioned load ya contract demand tak. Transformer par 100% tak, aur application mana karne ki jagah transformer badhana hai. Battery storage allowed. Saal ke end ka surplus sabse kam rooftop solar tariff par khareeda jata hai. | Zyada tar mills ko net metering milni chahiye; yahan zero export aksar paperwork ki dikkat hai, peechha kijiye |
Season se hi lagbhag sab tay hota hai
Rice mill ka saal dhaan ke saath chalta hai. Punjab mein 2026 ki kharif fasal ki khareed 1 October se shuru hui, aur state agencies ki custom milling wahan se tab tak chalti hai jab tak aapka allotment chale. Phir mill shaant. Roller flour ya atta mill saal bhar gehun khareedti hai aur kaafi seedhi chalti hai.
Battery ke liye iska do tarah se asar hai. Pehla, battery tabhi kamaati hai jab dopahar ke surplus se charge ho kar usi shaam ya agli subah chalti mill ko units lauta sake. Off-season mein surplus bahut hai par dene ke liye load nahi, na din mein na raat mein, to battery bhari padi rehti hai. Doosra, off-season ka surplus theek wahi hai jismein net metering kaam aati hai: bank hui units milling ke mahino mein jaati hain. Punjab ka 2024 ka rice sheller ke liye April-March saal isi pattern mein fit baithta hai.
Isliye milling days imaandari se giniye. Jo mill 6 mahine, mahine mein 26 din chalti hai, uske saal bhar ke average mein mahine ke 13 milling days hain, aur neeche calculator mein yahi number daaliye.
Parboiling unit ya husk wala boiler aur dryer bhi load pattern badalte hain, aksar din mein motor load badhate hain. Form mein likh dijiye; yeh sizing ka hissa hai.
Battery mein rakhi solar unit mill ke bill par kitne ki
Battery jo leti hai uska lagbhag 85% lautati hai. Grid ki bijli lagbhag ₹9 unit ho to dopahar mein rakhi aur baad mein use hui har solar unit lagbhag ₹7.7 bachati hai. Agar woh unit export ho kar credit kamaa sakti thi, to woh credit ghata dijiye.
Isliye export ka hisaab is sum ka sabse bada number hai. Zero export ya lapse hote surplus par rakhi unit ki poori keemat hai. Apne hi rate par net metering ho to grid pehle se unit bank kar raha hai, aur battery kam hi jodti hai.
Calculator sirf milling days ka roz ka surplus ginta hai. Grid cut mein chalta solar, bacha diesel, demand charge aur ToD peak rate isme nahi gine.
Apni mill ke solar plant se hisaab lagaiye
Inverter app aur bill se paanch number. Jab tak aap humse check karne ko na kahein, kuch kahin nahi jata.
Figures dekhne ke liye plant ka size aur waste hone wala hissa daaliye.
Yeh hisaab kaise lagaya
- Solar average din mein lagbhag 4.25 unit per kWp banata hai. Monsoon aur sardi ke dhundhle din kam.
- Jo hissa aap daalte hain woh milling day ka roz ka surplus hai. Sirf milling days gine jaate hain: 6 mahine, 26 din chalne wali rice mill 13 daale. Off-season ka surplus chhod diya kyunki use dene ke liye load nahi.
- Battery itni li gayi ki woh surplus ek charge mein aa jaye, rated kWh ka lagbhag 90% use karke, aur har milling day ek baar bhare aur khaali ho.
- Battery jo leti hai uska lagbhag 85% lautati hai. Lautai har unit aapka daala grid rate bachati hai; jo unit ab export nahi hui uska daala credit ghataya gaya.
- Lagwane ka kharcha 250 kWh se chhoti battery ke liye ₹25,000 se ₹38,000 per kWh, aur usse badi ke liye ₹20,000 se ₹30,000 per kWh liya gaya, GST alag. Yeh mota range hai, quote nahi.
- Nahi gina: grid cut mein chalta solar, bacha diesel, ToD peak rate, demand charge, aur saalon mein battery ki ghatti capacity.
- Yeh pehla andaaza hai. Koi bhi keemat dene se pehle aapka load pattern, motor starting, export rules aur tariff check kiye jaate hain.
Apni mill ka figure check karwaiye
Naam aur number chhod dijiye. Hum call karke batayenge ki aapka solar kitna kho raha hai aur aapki mill mein battery ya koi sasta upay kya theek hai.
Apni mill aur uske solar ke baare mein bataiye ↓Example: zero export par 300 kWp wali mill, saal bhar aur seasonal
Yeh samjhane ke liye hai, koi asli mill nahi. Input: 300 kWp panel, milling day ka 20% solar break, shift change aur line rukne par kata, mahine mein 26 milling days, zero export, grid ₹9 unit. Yeh calculator ka hi hisaab hai, upar yahi numbers daaliye to yahi result aayega.
Plant average din mein lagbhag 1,275 unit banata hai aur unme se lagbhag 255 kat jaati hain. Inhe rakhne ke liye 290 kWh ki battery. Agar mill saal bhar chale, jaise zyada tar flour mill, to battery saal mein lagbhag ₹6.1 lakh bachati hai, lagwane ka kharcha lagbhag ₹58 lakh se ₹87 lakh, aur payback lagbhag 9.5 se 14 saal.
Ab wahi rice mill saal mein 6 mahine chale, yaani saal bhar ke average mein mahine ke 13 milling days. Battery aur uska kharcha wahi, bachat aadhi ho kar lagbhag ₹3.0 lakh saal, aur payback lagbhag 19 se 29 saal tak khinch jata hai. Off-season mein plant mahine mein lagbhag 38,250 unit banata hai aur zero export par lagbhag saari kho jaati hain; battery inhe nahi bacha sakti kyunki kuch chal hi nahi raha.
Ab export allow hone se milaiye. Sirf milling days ki kati units saal mein lagbhag 79,560 hain, jo grid rate par lagbhag ₹7.2 lakh ki hain agar net metering se mill inhe poora use kar sake, bina battery khareede, aur off-season ki units upar se.
Input badliye to jawab kaafi badalta hai. Peak rate wali shaam ki shift, ya din ke cut jinme DG chalta hai, battery ka case sudhaarte hain; kam curtailment ya kam milling days use bigaadte hain.
Battery se pehle yeh try kijiye
- Net metering ya zyada export limit ke liye apply kijiye, aur mana hua ho to likhit mein wajah maangiye. Punjab mein rooftop solar ke liye transformer upgrade ab DISCOM ka kaam hai (2025), aur rice sheller ka settlement April se March hai (2024).
- Agar plant aapke state ki sanctioned load wali limit se bada hai, to sanctioned load badhwane ka kharcha battery ke kharche se milaiye.
- Jahan process allow kare, colour sorter, grading, packing line aur bran handling solar ke ghanton mein chalaiye, aur lunch ke ghante mein bhi chalu rakhiye.
- Paddy line aur polishing line ka lunch, ya roller mill ki shifton ka break, aage peeche kijiye, taaki 1 baje saara load ek saath na gire.
- Borewell aur paani ke pump, parboiling ka paani bharna aur godown ke fan par timer lagaiye taaki yeh 11 se 3 baje ke beech chalein.
- Solar installer se export controller ka margin check karwaiye. Margin ka har kW poore din katta hai.
- Zero export par rehte hue aur panel mat lagwaiye. Har extra kWp zyada tar curtailment hi badhata hai.
Huller, polisher aur roller ki motor: battery inverter ko kya sambhalna hai
Mill induction motors se bhara kamra hai jo load par start hoti hain: huller, polisher, whitener, elevator, blower aur roller mill. Har motor start hote waqt kuch second apne running current se kai guna current kheenchti hai. Grid par transformer ise jhel leta hai. Agar battery ko grid cut mein mill bhi chalani hai, to uska inverter (PCS) yeh starting current khud dega, isliye use sirf running kW nahi, starting surge ke hisaab se lena padta hai.
Aam upay: motor ek saath nahi, ek ke baad ek start kijiye, badi motor par lage star-delta starter, soft starter ya VFD ka use kijiye, aur designer ke saath pakka kijiye ki battery ko kaunsi motor start karni hai. Agar battery sirf bacha solar rakhti hai aur grid hamesha hai, to yeh kaafi kam maayne rakhta hai.
Bhoosi, bran ki dhool aur garmi: battery kahan rakhein
Mill mein bhoosi, bran aur aate ki dhool har jagah pahunchti hai aur battery cabinet ko thanda rakhne wale filter aur fan bhar deti hai. Cabinet band, saaf kamre mein ya sealed outdoor enclosure mein rakhiye, bhoosi ke yard, bran room, boiler aur dryer se door, seedhi dhoop se bacha kar, aur paani se upar plinth par. Poochhiye ki aapki dhool mein filter kitni baar saaf karne padenge, aur kaun karega.
Lithium iron phosphate (LFP) cabinet lijiye jinme apna battery management, cooling aur fire detection ho, aur unke aas paas bhoosi aur bori mat rakhiye. Jagah site visit par hi tay kijiye, keemat final hone se pehle.
Kharcha aur battery ki umar, short mein
Mota hisaab: lagi hui system lagbhag ₹20,000 se ₹35,000 per kWh battery padti hai, GST alag, chhoti system per kWh mehngi; is keemat mein kya aata hai woh India mein battery ke kharche wale guide mein hai, link neeche. Chalti mill mein solar battery har milling day lagbhag ek cycle chalti hai, isliye warranty mein cycle ka number saal jitne dhyan se padhiye. Seasonal mill kam cycle chalati hai, isse battery sasti nahi hoti; bas payback lamba hota hai.
Mill ke liye battery kab layak nahi
- Aapko net metering ya zyada export limit mil sakti hai. Pehle wahi kijiye; usi surplus se bahut kam kharche mein kamaai.
- Aapka surplus zyada tar off-season aur weekly off ka hai. Battery band mill mein units nahi khiska sakti.
- Mill sirf din mein chalti hai aur solar din ke load se chhota hai. Rakhne ko surplus hi nahi.
- Rakhi units use karne ke liye na shaam ya raat ka load hai, na din ke regular cut. Battery dopahar ko bhar jaati hai aur khaali hone ki jagah nahi.
- Rakhne ki jagah sirf line ke paas bhoosi aur dhool mein hai. Pehle jagah ka hal nikaaliye.
Agar aapki mill mein asli dikkat cut aur DG hai aur solar baad ki baat, to diesel ka hisaab DG wali factory ke guide mein hai.
Turnkey: pehli jaanch se aakhri service visit tak ek hi team
Aapko battery company, inverter supplier, electrician aur maintenance wale alag-alag dhoondh kar unhe ek saath bithaane ki zaroorat nahi. Ingro mill ka poora project sambhalta hai: bill aur inverter data se dekhta hai ki net metering, load ka badlaav ya battery mein kya theek hai, aapke solar aur motors ke hisaab se system design karta hai, kisi bhi company ki battery Ingro EMS ke saath laata hai, lagaata aur chalu karta hai, civil aur electrical kaam karta hai, DISCOM aur inspector ke approval mein madad karta hai, aur lambe samay tak maintenance karta hai.
Shuruaat neeche ke form se hoti hai: mill ke baare mein bataiye, engineer aapke case par free salah dega. Agar battery aapke liye faayde ki nahi, to hum saaf bata denge.
Sign karne se pehle yeh poochhiye
- Normal milling day par meri kati units mein se kitni yeh pakdegi, aur kis data se hisaab lagaya?
- Jin mahino mill band rehti hai, un mahino mein yeh mere liye kya karegi?
- Kya aapne check kiya ki iski jagah mujhe net metering ya zyada export limit mil sakti hai, aur usse kitna milta?
- Payback mere saal ke asli milling days par nikala hai, ya baarah mahine 26 din maan kar?
- Inverter ko kaunsi motor start karni hain, aur huller aur polisher ek saath start hon to uska size kaise liya?
- Battery controller mere export controller aur reverse power relay ke saath kaise chalega, aur DISCOM mein badlaav ki file kaun lagayega?
- Cabinet kahan khada hoga, bhoosi aur dhool se kaise bachega, aur warranty kitne saal aur kitne cycle ki?
Aage kaam ka
- Rooftop solar wali factory: zero export ka poora guide
- DG wali factory: battery ya diesel
- Cold storage: season bhar battery backup
- India mein battery system ka kharcha
- PCS (battery inverter) jo motor start kar sakein
- India mein bikne wale solar inverter
- BESS cabinet, unki specifications ke saath
- Turnkey battery system: design se O&M tak ek hi team
Mill ke malik yeh poochhte hain
Lunch ke waqt meri mill ka solar graph flat ho jata hai. Kya yeh zero export hai?
Aksar haan. Huller aur polisher rukte hi export controller inverter ko utna kaat deta hai jitna abhi chal raha hai. Flat hisse ke upar jo gaya, woh phenka hua solar hai.
Battery khareedne ki jagah net metering apply karun?
Agar plant ka size, sanctioned load aur transformer allow karein, to haan: bahut sasta padta hai. Example mein sirf milling days ki kati units grid rate par saal mein lagbhag ₹7.2 lakh ki hain. Battery wahan theek hai jahan export mana ho, cap ho ya kam rate par credit ho.
Kya battery off-season mein mera solar use karegi?
Zyada nahi. Battery units ko kuch ghante hi khiskati hai, aur woh bhi chalti mill mein. Mill band ho to dene ki jagah nahi. Jahan allowed ho, off-season ki units ko milling mahino tak net metering hi le jaati hai.
Punjab mein rice sheller ka settlement April se March hai. Iska matlab?
PSERC ke 2024 amendment mein rice sheller aur doosri seasonal industry ka net metering hisaab 1 April se 31 March chalta hai. Off-season mein bank hui units October se March ke milling bill mein adjust ho sakti hain, phir hisaab reset hota hai.
Grid jaane par kya battery huller chala sakti hai?
Chala sakti hai agar inverter motor ke starting current ke hisaab se liya ho aur motor ek ke baad ek start hon. Isse inverter bada aur mehnga hota hai, isliye tay kijiye ki sach mein kaunsi line chahiye.
Rice mill mein battery par koi subsidy hai?
Humein koi kendriya ya state scheme nahi mili jo saaf taur par rice ya atta mill ki battery ko cover kare. Apne state ke udyog ya food processing vibhag se poochhiye, aur bharosa karne se pehle likhit mein lijiye.
Sources
- PSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems) Regulations, 2021, Punjab (Notification No. 158, 18 Aug 2021)
- PSERC rooftop solar (1st amendment) Regulations, 2024 (Notification No. 186, 11 Mar 2024): April to March settlement for rice shellers
- PSERC rooftop solar (Second Amendment) Regulations, 2025 (Notification No. 193, 20 Feb 2025): transformer upgrades by the DISCOM
- PowerPeak Digest (April 2026): PSERC Third Amendment, 2026, net metering ceiling, behind the meter, year-end settlement
- Renewable Watch (30 Jun 2021): Electricity (Rights of Consumers) Amendment Rules, 2021, net metering up to 500 kW
- SolarQuarter (13 Mar 2026): draft Electricity (Rights of Consumers) Amendment Rules, 2026, storage above 500 kW
- CBIP summary of the UPERC (Rooftop Solar PV Grid Interactive Systems Gross / Net Metering) Regulations, 2019, Uttar Pradesh
- pv magazine India (12 Feb 2019): UP's 2019 rules keep net metering for residential and agricultural consumers only
- CSERC (Grid Interactive Distributed Renewable Energy Sources) Regulations, 2019, Chhattisgarh (CBIP copy)
- The Week / PTI (6 Nov 2026): Punjab paddy procurement began on 1 October
In sites ko battery storage se fayda hua
Alag-alag sites, ek hi baat: apni solar aur green bijli zyada istemaal kijiye, bijli ka bill ghataiye, aur grid saath na de tab bhi kaam chalta rahe.
LiveAPAR Industries · Factory · 720 kW / 500 kWh batteryA factory whose process lines keep running through every dip in power.
- <1 ms
- response when the load jumps or the grid dips
- Zero
- gaps in power to the production lines
- End to end
- battery, PCS, controls and installation by one team
LiveEV charging hub · 260 kW / 580 kWh battery · IndiaElectric buses and cars keep charging, even when the grid is gone.
- 2.5×
- charging power from the same grid connection
- 1 s
- battery and PCS data, cell by cell
- Grid outage
- buses and cars still charge off the battery
UnderwaySolar + battery micro-grid · Melghat, MaharashtraA village without a grid. A solar and battery micro-grid that powers it.
- Village
- no grid connection
- Black start
- from standstill, no outside source
- 820
- homes on solar and battery
In testingIndustrial battery plant · Pune · 2.5 MW / 10 MWhTwo battery containers, two vendors, two languages. One EMS runs them as one plant.
- 2
- container makes, each with its own BMS protocol
- 1
- PCS and one EMS across both
- Hot-swap
- take a container out for service, plant keeps running
Apni mill aur uske solar ke baare mein bataiye
Jo pata hai bhej dijiye. Ingro ka engineer aapki mill par free salah dega: solar kahan kho raha hai, net metering, load ka badlaav ya battery mein kya theek hai, aur size, kharcha aur payback kitna. Aage badhe to baaki sab hamari team sambhalegi: site ki jaanch, design, installation, approval mein madad, commissioning aur O&M.
Aage kya hoga: hum ek working day ke andar phone ya WhatsApp par jawab denge. Abhi site visit ki zaroorat nahi, aur koi paisa nahi lagta.