Aug 2024
CERC
Charges for deviating from schedule in the inter-state grid, with separate rules for wind and solar, standalone storage and co-located storage. In force from 16 September 2024.
What it changes: Tighter deviation bands for solar and wind make forecasting and EMS-driven storage dispatch worth money, and co-located storage is settled by operating mode.
Sep 2023
Ministry of Power
Policy, regulatory and financial measures to deploy battery and pumped storage. Dated August 2023, released September 2023.
What it changes: The umbrella policy behind later storage measures such as VGF, ISTS waivers and BESS procurement rules.
Sep 2023
Union Cabinet / Ministry of Power
₹3,760 crore of VGF for 4,000 MWh of battery storage, to be built by 2030-31.
What it changes: The first central support for grid-scale BESS, lowering storage tariffs in state tenders.
Jun 2023
Ministry of Power
Makes Time-of-Day tariffs compulsory. C&I consumers above 10 kW maximum demand move to ToD tariffs no later than 1 April 2024.
What it changes: Peak rates at least 20% above normal and solar-hour rates at least 20% below give C&I sites a clear gap for EMS-scheduled battery charging and peak shaving.
May 2023
CERC
A new grid code for planning, connection, commissioning, scheduling and operation, treating energy storage as its own class of grid user. In force from 1 October 2023.
What it changes: Commissioning a storage or RE plant depends on working plant controllers, telemetry and active-power control, all delivered through the EMS.
Jul 2022
Ministry of Power
RPO trajectory for distribution companies and open-access consumers, with a separate energy storage obligation rising each year.
What it changes: Discoms and large consumers must hold a growing share of energy from storage charged by renewables.
Mar 2022
Ministry of Power
Standard bidding framework for BESS as generation, transmission or distribution assets and for ancillary services.
What it changes: The basis for most state and central BESS tenders since.
Jan 2022
CERC
Secondary and tertiary reserve services procured through the market, open to energy storage and demand response. Most provisions in force from 5 December 2022.
What it changes: A BESS can earn ancillary-services revenue if its EMS supports two-way RLDC communication, SCADA telemetry and a 30-second response.